Hwange Unit 7 Achieves 335MW Full Capacity Output

Everything You Need To Know About Hwange Unit 7 and Why It Will Not end Load shedding!

Hwange Thermal Power Station’s Unit 7 first achieved a full capacity output of 335MW at 9:27 AM on Thursday 30th March 2023.

The Zimbabwe Power Company (ZPC) managed to synchronise the first of two generators on Unit 7 into the national grid on Monday, 20 March after failing to do so several times.

The two generators make up the Hwange Thermal Power Station Unit 7 and 8 Expansion Project being installed under a US$1.4 billion facility from China Eximbank.

Soon after the successful synchronisation of Unit 7 into the national grid, ZPC said power will be progressively fed into the grid until it reaches 300MW.

However, captains of industry said Unit 7 will not meaningfully end the current electricity challenges bedeviling the economy.

Advertisement. Scroll to continue reading.

Zimbabwe has a national electricity peak demand of between 1 700 and 2 200 depending on the season.

On 31 March 2023, ZPC was generating a total of 678MW, with Hwange producing 311, Kariba, 350, and Munyati 17. Harare and Bulawayo were generating zero.

span style=”color: #ff0000″>In other news,

MAN CAUSES SCENE AT WIFE’S WORKPLACE

A man caused a scene at his wife’s workplace in Harare yesterday, accusing her of infidelity. Tinashe Ganiwa said his wife of 12 years, Virginia Ganiwa, was seeing her married driving instructor, Six Mukwidze.

MAN CAUSES SCENE AT WIFE’S WORKPLACE

He claimed that the two met when his wife was a learner driver in Belvedere sometime last year.

Advertisement. Scroll to continue reading.

He told H-Metro that the cheats took their relationship to another level when they visited Virginia’s parents…Continue Reading

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Catch More Updates Below

LOCAL NEWS

As the government takes steps to reduce load-shedding, which will increase industrial productivity, Hwange Thermal Power Station Unit 7, which was recently removed off...

BUSINESS NEWS

Hwange Thermal Power Station Unit 7, which was recently taken off the national grid for further tests, will be back online on Monday, adding...

LOCAL NEWS

Captains of industry say the successful synchronisation of Hwange Thermal Power Station’s Unit 7 with a generation capacity of 300 megawatts (MW) with the...

Sports News

Dynamos wary of newly-promoted teams. The Harare giants, who are looking to improve on their third-place finish last year, travel to Hwange for their...

BUSINESS NEWS

Power challenges will be dramatically ameliorated as Government is working on the “best and most” reliable power supply, President Mnangagwa said yesterday. With the...

Advertisement