Home LOCAL NEWS COVID-19 Delays Kariba Power Station Upgrade By A Further 2 Years

COVID-19 Delays Kariba Power Station Upgrade By A Further 2 Years

Kariba Hydro Power station tipped to increase output

The COVID-19 pandemic has reportedly set back the Kariba Power station upgrade by a further 2 years.

The development reportedly came to light after Zambia’s finance minister met Zimbabwe’s Finance Minister.

Delays in unforeseen technical challenges, supply constraints, and delays in contracting works have also been cited apart from the ongoing COVID-19 pandemic.

According to the publication:

The ministers approved a budget of $71.3 million for 2021 that will be financed through a combination of internally generated funds, amortized loans, and grants sourced from the World Bank, African Development Bank, the European Union, and the Swedish International Development Agency.

Meanwhile, the Batoka Gorge Project is expected to break ground later this year.

Source | BNN Bloomberg

Also Trending...

Woman Caught Bedding 13 year old, Claims He Invited Her!

A Greendale woman was on Tuesday arrested after she was caught having s..ex with a 13-year-old boy at the latter’s parents’ home in Houghton Park. Woman Caught Bedding 13 year old, Claims He Invited Her! The unidentified woman was quick to defend herself from arresting police officers by showing them condoms, saying they had had protected...Read More